Assessment Activities
Property Name | EPA Funding | Completion Date | Activity | Leveraged Funding |
Former Banner Fiberboard Site | $51,000.00 | 04/03/2012 | Phase II Environmental Assessment | $0.00 |
Former GenPak Site | $7,500.00 | 09/27/2013 | Phase I Environmental Assessment | $0.00 |
Former TS&T Pottery Site | $0.00 | 06/30/2011 | Phase I Environmental Assessment | $11,400.00 |
Former TS&T Pottery Site | $62,700.00 | 05/31/2013 | Phase II Environmental Assessment | $4,000.00 |
Jimmy Carey Stadium | $6,800.00 | 09/25/2013 | Phase I Environmental Assessment | $0.00 |
EPA Assessment Funding: $128,000.00
Leveraged Funding: $15,400.00
Total Funding: $143,400.00
NOTE: Funding marked for deletion not included in totals