131901
4266 McRee Avenue St. Louis City, MO 63110
.14
15445000010
38.619387 / -90.255563
1
Klein, Susan
Klein.Susan@epa.gov
913-551-7786


Top of Page


Property Location



Top of Page


Property Progress


Top of Page


CAs Associated with this Property

CA NameCA #StateTypeAnnouncement Year
St. Louis Development Corporation2B97708601MOBCRLF2009


Top of Page


Assessment Activities at this Property

ActivityEPA FundingStart DateCompletion DateCAAccomplishment Counted?Counted When?
Phase I Environmental Assessment08/01/201008/31/2010St. Louis Development CorporationN


Is Cleanup Necessary? Yes
EPA Assessment Funding:
Leveraged Funding: $2,000.00
Total Funding: $2,000.00


Top of Page


Climate Adaption and Mitigation - Planning or Assessment

There is no data for Climate Adaption and Mitigation - Planning or Assessment.


Top of Page


Contaminants and Media


Petroleum Products
Cleaned Up
Ground Water
Soil
Cleaned Up
Cleaned Up

Cleanup Activities

Start DateEPA FundingCompletion DateCAAccomplishment Counted?Cleanup Documentation
04/25/2011$46,000.0005/25/2011St. Louis Development CorporationNo


Cleanup/Treatment Implemented:
Cleanup/Treatement Categories:
Addl Cleanup/Treatment info:
Address of Data Source:
Total ACRES Cleaned Up: .14
Number of Cleanup Jobs Leveraged: 3
EPA Cleanup Funding: $46,000.00
Leveraged Funding:
Cost Share Funding:
Total Funding: $46,000.00


Top of Page


Climate Adaption and Mitigation - Demolition or Cleanup

There is no data for Climate Adaption and Mitigation - Demolition or Cleanup.


Top of Page


Institutional and Engineering Controls

No
No


Top of Page


Redevelopment and Other Leveraged Accomplishments

Start DateLeveraged FundingCACompletion Date
04/03/2012$400,000.00St. Louis Development Corporation10/23/2012


Number of Redevelopment Jobs Leveraged:
Actual Acreage of Greenspace Created:
Leveraged Funding:


Top of Page


Climate Adaption and Mitigation - Redevelopment

There is no data for Climate Adaption and Mitigation – Redevelopment


Top of Page


Additional Property Attributes

On December 21, 2010, SLDC entered into a subagreement with Garden District Commission for an amount up to 40,000 for tank and contamination removal at the site (a former gas station). The Garden District Commission (GDC)(www.gardendistrictcommission.org) is a charitable neighborhood advocacy primarily for the Shaw, McRee Town, Tiffany, and Southwest Garden Neighborhoods. In May 2011, three underground storage tanks and tank piping were removed along with 4300 gallons of water and residual product and 200 cubic yards of contaminated soil. Based on the confirmation sampling results following tank closure and soil removal, residual soil and groundwater contamination exists onsite. Site characterization and risk assessment are recommended however cleanup is substantially complete and further monitoring is likely all that will be required. The subgrant amount was increased to 46000 due to monitoring costs. In 2012 the parcel was combined with an adjoining residential parcel and a �Olio� and �Elaia� wine bar and restaurant was opened late 2012 (www.oliostl.com also https://www.facebook.com/ElaiaOlio.)

Former Use: On December 21, 2010, SLDC entered into a subagreement with Garden District Commission for an amount up to 40,000 for tank and contamination removal at the site (a former gas station). The Garden District Commission (GDC)(www.gardendistrictcommission.org) is a charitable neighborhood advocacy primarily for the Shaw, McRee Town, Tiffany, and Southwest Garden Neighborhoods. In May 2011, three underground storage tanks and tank piping were removed along with 4300 gallons of water and residual product and 200 cubic yards of contaminated soil. Based on the confirmation sampling results following tank closure and soil removal, residual soil and groundwater contamination exists onsite. Site characterization and risk assessment are recommended however cleanup is substantially complete and further monitoring is likely all that will be required. The subgrant amount was increased to 46000 due to monitoring costs. In 2012 the parcel was combined with an adjoining residential parcel and a �Olio� and �Elaia� wine bar and restaurant was opened late 2012 (www.oliostl.com also https://www.facebook.com/ElaiaOlio.)
Commercial (.14)
Petroleum
Enrolled: 01/21/2011