Cleanup Activities
Start Date | EPA Funding | Completion Date | CA | Accomplishment Counted? | Cleanup Documentation |
11/26/2013 | | 03/29/2023 | The Atlanta Development Authority | Yes | |
11/26/2013 | $146,501.72 | 03/29/2023 | The Atlanta Development Authority | Yes | |
Cleanup/Treatment Implemented:
Y
Cleanup/Treatement Categories:
Addl Cleanup/Treatment info:
The Revised Draft Interim Compliance Status Report documents impacted soil excavation and disposal was submitted on 12/21/16 to EPA. Approx. 1,668 tons of impacted soil was excavated and transported for off-site disposal at a Subtitle D landfill. Clean soil replaced excavation area.
Address of Data Source:
Total ACRES Cleaned Up: 21.98
Number of Cleanup Jobs Leveraged: 8
EPA Cleanup Funding: $146,501.72
Leveraged Funding:
Cost Share Funding: $36,973.08
Total Funding: $183,474.80