214861
347-399 Bridges to Buttes Byway Gordon, NE 69343
3.84
810085461
42.79976684657473 / -102.1994244073486
3
Morris, Jennifer
Morris.Jennifer@epa.gov
913-551-7341


Top of Page


Property Location



Top of Page


Property Progress


Top of Page


CAs Associated with this Property

CA NameCA #StateTypeAnnouncement Year
Nebraska Department of Environmental QualityRP98732204NESection 128(a) State/Tribal2011
Nebraska Department of Environmental QualityRP98732205NESection 128(a) State/Tribal2015


Top of Page


Assessment Activities at this Property

ActivityEPA FundingStart DateCompletion DateCAAccomplishment Counted?Counted When?
Phase I Environmental Assessment$18,818.0010/09/201406/24/2015Nebraska Department of Environmental QualityYFY16


Is Cleanup Necessary? Yes
EPA Assessment Funding: $18,818.00
Leveraged Funding:
Total Funding: $18,818.00


Top of Page


Climate Adaption and Mitigation - Planning or Assessment

There is no data for Climate Adaption and Mitigation - Planning or Assessment.


Top of Page


Contaminants and Media


Chromium (Cr)
Lead
Other Metals
Petroleum Products
SVOCs
VOCs
NOT Cleaned up
NOT Cleaned up
NOT Cleaned up
Cleaned Up
NOT Cleaned up
NOT Cleaned up
Ground Water
Soil
Surface Water
NOT Cleaned up
NOT Cleaned up
Cleaned Up

Cleanup Activities

Start DateEPA FundingCompletion DateCAAccomplishment Counted?Cleanup Documentation
08/13/201801/30/2020Nebraska Department of Environmental QualityNo
08/13/2018$100,000.0001/30/2020Nebraska Department of Environmental QualityNo


Cleanup/Treatment Implemented:
Cleanup/Treatement Categories:
Addl Cleanup/Treatment info: Removal of contaminated water in on-site sludge pits; solidification and disposal of sludge.
Address of Data Source:
Total ACRES Cleaned Up: 3.84
Number of Cleanup Jobs Leveraged: 6
EPA Cleanup Funding: $100,000.00
Leveraged Funding: $234,104.94
Cost Share Funding:
Total Funding: $334,104.94


Top of Page


Climate Adaption and Mitigation - Demolition or Cleanup

There is no data for Climate Adaption and Mitigation - Demolition or Cleanup.


Top of Page


Institutional and Engineering Controls

No
No
No
No


Top of Page


Redevelopment and Other Leveraged Accomplishments

There are no current redevelopment activities.


Number of Redevelopment Jobs Leveraged:
Actual Acreage of Greenspace Created:
Leveraged Funding:


Top of Page


Climate Adaption and Mitigation - Redevelopment

There is no data for Climate Adaption and Mitigation – Redevelopment


Top of Page


Additional Property Attributes

The property contains an open pit that holds a thick tar-like substance. The pit served as a disposal area for the byproducts of the refinery process. Sampling of the pit revealed elevated concentrations of chrysene and contained 11.3% total petroleum hydrocarbons by sample weight. Five ground water samples taken from private wells down-gradient of the site revealed no VOC or SVOC contamination. Several Recognized Environmental Conditions (RECs) are associated with the site and include the open pit, an unknown area on the west-central portion of the property where the pit contents were mixed with soil, inaccessible buildings and Aboveground Storage Tanks (ASTs), several areas with stained soil, and an unknown number of 55-gallon drums. Limited access to the site resulted in significant data gaps. Former Use: The site was the location of an oil and gas refinery that was in operation between the 1930s-1950s. Evidence of the past activity remains in the form of above-ground storage tanks (ASTs), buildings, and an open disposal pit containing sludge. The property is currently being used for storage of vehicles, farming equipment, and construction materials. Beginning in 2018, remedial work began related to the two open sludge pits on the property. Around 150,000 gallons of waste water were drained out of the pits and discharged under a general permit. The remaining sludge in the bottom of the drained pits was stabilized by the addition of hundreds of cubic yards of broken concrete that had been stockpiled on the property and additional concrete provided by the City of Gordon. The remaining space was filled with clean soil to two feet above grade to ensure positive drainage away from the former pits.
Industry (3.84)