104 Butler Street Meriden, CT 06451
3.75
41.5365767 / -72.8060524
5
Castagna, Kathleen
castagna.kathleen@epa.gov
617-918-1429


Top of Page


Property Location



Top of Page


Property Progress


Top of Page


CAs Associated with this Property

CA NameCA #StateTypeAnnouncement Year
Meriden, City ofBF97114801CTAssessment2004
Meriden, City ofBF97182101CTAssessment2007
Meriden, City ofBF97182301CTCleanup2007
R1 TBA - Connecticut (Pre-law Superfund TBA)n/aCTTBA1998


Top of Page


Assessment Activities at this Property

ActivityEPA FundingStart DateCompletion DateCAAccomplishment Counted?Counted When?
Phase I Environmental Assessment$5,000.0007/10/1997R1 TBA - Connecticut (Pre-law Superfund TBA)N
Phase I Environmental Assessment$2,200.0002/09/200604/24/2006Meriden, City ofYFY08
Phase II Environmental Assessment$52,125.0002/09/200603/28/2007Meriden, City ofN
Phase II Environmental Assessment$35,000.0009/10/1999R1 TBA - Connecticut (Pre-law Superfund TBA)N
Supplemental Assessment$21,250.0001/14/200908/31/2009Meriden, City ofN
Supplemental Assessment$17,325.0003/28/2007Meriden, City ofN


Is Cleanup Necessary? Yes
EPA Assessment Funding: $132,900.00
Leveraged Funding:
Total Funding: $132,900.00


Top of Page


Climate Adaption and Mitigation - Planning or Assessment

There is no data for Climate Adaption and Mitigation - Planning or Assessment.


Top of Page


Contaminants and Media


Asbestos
Lead
Other Metals
PAHS
Petroleum Products
VOCs
Cleaned Up
NOT Cleaned up
NOT Cleaned up
NOT Cleaned up
NOT Cleaned up
NOT Cleaned up
Ground Water
Soil
NOT Cleaned up
NOT Cleaned up

Cleanup Activities

Start DateEPA FundingCompletion DateCAAccomplishment Counted?Cleanup Documentation
02/03/2008Meriden, City ofNo


Cleanup/Treatment Implemented:
Cleanup/Treatement Categories:
Addl Cleanup/Treatment info:
Address of Data Source:
Total ACRES Cleaned Up: 3.75
Number of Cleanup Jobs Leveraged:
EPA Cleanup Funding:
Leveraged Funding: $50,000.00
Cost Share Funding:
Total Funding: $50,000.00


Top of Page


Climate Adaption and Mitigation - Demolition or Cleanup

There is no data for Climate Adaption and Mitigation - Demolition or Cleanup.


Top of Page


Institutional and Engineering Controls

Yes
Proprietary Controls Government Controls Information Devices
No


Top of Page


Redevelopment and Other Leveraged Accomplishments

There are no current redevelopment activities.


Number of Redevelopment Jobs Leveraged:
Actual Acreage of Greenspace Created:
Leveraged Funding:


Top of Page


Climate Adaption and Mitigation - Redevelopment

There is no data for Climate Adaption and Mitigation – Redevelopment


Top of Page


Additional Property Attributes

Supplemental Investigation Report was completed Q3 2009. The purpose of this investigation was to refine the conceptual site model, better define remediation limits and evaluate site soil for potential reuse.

Former Use: 104 Butler Street is 3.75 acres and sits east of Harbor Brook. Approximately half the site is located within the 100-year flood plain. The site is zoned for manufacturing use. The site contains a 7,200 sq ft former power plant and associated heat conveyance piping. In 1884, Parker Bros. Machine Shops and Gun Factory facility were in operation. Industrial operations included gun manufacturing, specifically consisting of a foundry and machining activities. In 1939 the International Silver Co. was in operation at the site, involved in silverware manufacturing. Processes included casting, plating, machining, trimming, polishing, buffing, forging, storage, and shipping. The site is currently occupied by heat conveyance piping and the former power plant building. The remainder of the site is vacant cleared space. The City of Meriden recently acquired the property.
Industry (3.75)