Profile Information

Government
170106
6 South Central Avenue Cut Bank, MT 59427
.5
2
48.6363026 / -112.3327349
1
Shen, Stephanie
shen.stephanie@epa.gov
303-312-6184


Top of Page


Property Location



Top of Page


Property Progress


Top of Page


CAs Associated with this Property

CA NameCA #StateTypeAnnouncement Year
Montana Department of Environmental Quality RP98881114MTSection 128(a) State/Tribal2013
R8 TBA - Montana (STAG Funded)n/aMTTBA2004


Top of Page


Assessment Activities at this Property

ActivityEPA FundingStart DateCompletion DateCAAccomplishment Counted?Counted When?
Phase I Environmental Assessment$4,000.0008/26/201301/31/2014R8 TBA - Montana (STAG Funded)YFY14
Phase II Environmental Assessment$14,700.0008/26/201301/31/2014R8 TBA - Montana (STAG Funded)N
Supplemental Assessment$8,050.0008/25/201601/04/2017Montana Department of Environmental Quality N


Is Cleanup Necessary? Yes
EPA Assessment Funding: $26,750.00
Leveraged Funding:
Total Funding: $26,750.00


Top of Page


Climate Adaption and Mitigation - Planning or Assessment

There is no data for Climate Adaption and Mitigation - Planning or Assessment.


Top of Page


Contaminants and Media


Asbestos
Lead
PCBS
NOT Cleaned up
NOT Cleaned up
NOT Cleaned up
Building Materials
NOT Cleaned up

Cleanup Activities

Start DateEPA FundingCompletion DateCAAccomplishment Counted?Cleanup Documentation
10/25/2016$69,317.9803/28/2017Montana Department of Environmental Quality Yes


Cleanup/Treatment Implemented: Y
Cleanup/Treatement Categories:
Addl Cleanup/Treatment info: Project included partial abatement and disposal of 740 square feet, 113 linear feet, and 8 windows of asbestos containing material (ACM) from the building interior. The remaining 3,550 square feet of ACM on the roof and second floor apartment siding were not abated during this project and will be removed at a later date.
Address of Data Source:
Total ACRES Cleaned Up: .5
Number of Cleanup Jobs Leveraged: 0
EPA Cleanup Funding: $69,317.98
Leveraged Funding:
Cost Share Funding:
Total Funding: $69,317.98


Top of Page


Climate Adaption and Mitigation - Demolition or Cleanup

There is no data for Climate Adaption and Mitigation - Demolition or Cleanup.


Top of Page


Institutional and Engineering Controls

No
No


Top of Page


Redevelopment and Other Leveraged Accomplishments

There are no current redevelopment activities.


Number of Redevelopment Jobs Leveraged:
Actual Acreage of Greenspace Created:
Leveraged Funding:


Top of Page


Climate Adaption and Mitigation - Redevelopment

There is no data for Climate Adaption and Mitigation – Redevelopment


Top of Page


Additional Property Attributes

Asbestos and lead-based paint (LBP) have been identified as contaminants present at the property. Non-friable asbestos and LBP (via encapsulation) could potentially be left in place with implementation of a maintenance plan. The contract for removal and disposal of asbestos-containing material at the Cut Bank Old Mercantile began on October 24, 2016 and was completed on March 28,2017. Asbestos abatement activities to be completed at a future date are the abatement and disposal of 2,000 square feet of black, grey, and white shingles and miscellaneous roofing materials containing asbestos, abatement and disposal of 1,000 square feet of black and grey tar and miscellaneous roofing materials containing asbestos, and abatement and disposal of 550 square feet of grey fibrous materials containing asbestos from under the second-floor apartment siding.

Former Use: The property was built in 1919 as Hosea Meat Market. It became Golden Rule Store and then Penny's Store in 1930. Glacier County owns the property due to tax delinquency and was hoping to demolish the building to provide a parking area for the neighboring Cut Bank Public Drug building.
Commercial (.16)
Enrolled: 08/25/2016
03/28/2017